Parametric cubic yardage, ACI 138 yield verification, and raw material takeoffs.
Define the baseline geometric volume of the pour before contingencies.
Deduct the exact cubic yardage displaced by the steel matrix and calculate pacing.
Verify delivery batch weights against tested unit weights to audit short loads.
97.2 CY
Gross Form Volume
92.6 CY
Net Yield
92.6 CY
Waste / Contingency (5%)
+ 4.6 CY
ACI 138 Truck Yield Validation
10.00 CY / TRUCK
1.029 REL YIELD
10
Trucks
2.0
Trk / Hr
4.9
Hours
Raw Mix Components (1:2:4)
21.4
Cement (CY)
42.8
Sand (CY)
85.6
Gravel (CY)
Flatwork Ancillaries
6-Mil Poly (20x100)
3 Rolls
Wire Mesh (w/ Overlap)
112 Sheets